Month 2 update — Oak Street Renovation
Completed
Demolition, rough plumbing, and electrical.
Renovation spending
$18,000 of $45,000 (40% of renovation budget)
Next work
Drywall, cabinets, and flooring.
Issue
Cabinet delivery delayed two weeks.
Response
Contractor resequenced work; target listing moved from Month 4 to Month 5.
Next update
Due in 30 days, with material changes reported sooner.